PROJECT ACTIVITY START FINISH
Design Activities Spring 2014 Spring 2017
Construction / Groundbreaking Summer 2015
Patrol Road West Fall 2016 Winter 2016/2017
Patrol Road East Winter 2016 Spring 2018
I-564 WB Fall 2016 Winter 2017/2018
I-564 EB Fall 2016 Winter 2017/2018
Hampton Blvd Bridge Winter 2016/2017 Winter 2017/2018
Boush Creek Bridges Winter 2016/2017 Winter 2017/2018
Ramp C. Flyover Bridge Spring 2016 Winter 2017/2018
Public Connector Winter 2016/2017 Summer 2017
CVIS Site Civil Spring 2017 Fall 2018
Gate 6/D Avenue Winter 2016/2017 Fall 2018
Intermodal EB & WB Fall 2016 Winter 2017/2018
Project Completion Fall 2018